Project title MARMARIS / AKSAZ TORPIDO AMMUNITION STORAGE FACILITIES

 

Project location MARMARIS
Owners Name and Address

Commencement date

REPUBLIC OF TURKEY MINISTRY OF NATIONAL DEFENCE NATI. INF. DEPT.

03.11.1998

Completion date 17.01.2002
Operating Firm E. H. ARUTAN Inc.
Associated Firms None
Description of project  Explosion proof and Burried SST-4MK-37 Tigerfish Torpido, Torpido Trunk Storage, Torpido Cap Storage, 2 each 200 tons ammunition storage, MK-46 MOD.5 Torpido Regulation Facility, Concrete pavement  and road, Forklift Garage, Unflemeabe Steel Storage, Fire Water Storage and Pump Station, Bile Treatment, Waste- water- sewage, Treatment, 9 ea. Forklifts, Water and Hydrant System, Lightining ststem, 1250 kVA Transformer Unit, 4 each 1500 kVA Frequence Convertors.