 Project title  | 
 KARADENİZ EREGLI – AMASRA FUEL TANKS  | 
| 
 Project location  | 
 ZONGULDAK – BARTIN REPUBLIC OF TURKEY  | 
| 
 Owners Name and Address Commencement date  | 
 REPUBLIC OF TURKEY MINISTRY OF NATIONAL DEFENCE NATI. INF. DEPT. 31.07.1992  | 
| 
 Completion date  | 
 19.08.1994  | 
| 
 Operating Firm  | 
 E. H. ARUTAN Inc.  | 
| 
 Associated Firms  | 
 NONE  | 
| 
 Description of project  | 
 – 6 each 2500 m3 fuel storage tanks – 2 each pumping stations -2 each 30 m3 sedimantation tanks – 13204 m2 epoxy eating – 1037 m 10” PE coatedsteel pipes – 1200 m 6” PE coated steel pipes – 2063 m 6” Galvanized steel pipes for fire – 14 each fire hyrant PN10 – 2620 m plastic coated wire fence – 610 m galvanized wire fence – 3 each main power distribution and control panels, – Cathodic Protections  |