Project title |
|
|
Project location | ÇORLU ÇERKEZKÖY, DİLOVASI, YALOVA, ORHANGAZİ, BURSA, ESKİŞEHİR | |
Owners Name and Address
Commencement date |
BOTAŞ STATE PIPELINE AUTHORITY 16.01.1991 |
|
Completion date | 30.07.1992 | |
Operating Firm | E.H. ARUTAN INC. | |
Associated Firms | None | |
Description of project | Construction p.e coated pipes of various diameters and length such as;
2” 14500 m 4”16500 m 6”18700 m 8” 28400 m 12” 37000 m 18” 5000 m
2 cach 75/129-28 bar Pressure Reducing and Metering Stations(Comprising heaters,filters, regulator sets.) with computer aided automatic control system 1 cach 16/4 Bar RMS’s and their related inlet valves and piping
|
|
HOT TIE IN | 36”x6” 24”x8” , 14”x4 various location HOT-TAPE has been carried out. | |
CROSSING | Various diameters such as: 8”, 10”, 12” 22” Road, motorway, railway ,crossing was completed with the horizontal road boring machine. | |
BENDING | Bending has been completed wit the Hydraulic Bending Machine and equipments various diameters such as; 6” 8”, 10”, 12” 20” | |
CATHODIC PROTECTION | The cathodic protection system designed in accordance with specification for cathodic protection.
The System finally designed and sized for a minimum limetime 20 years. |
|
COATING
TESTING AND COMMISSIONING |
Various diameters such as; 2”, 4”, 6” 8”, 12” Pipes have been coated with extruded polu-ethylene tape at our company’s mill
All pipelines and RMS’s station testing and commissioning has been completed by ARUTAN’s experienced professionals. |