| Project title |    EASTERN ANATOLIA PIPELINE SYSTEM DIESELIATION PHASE III
 
  | 
| Project location | MUŞ-DIYARBAKIR-BATMAN-KOVANCILAR REPUBLIC OF TURKEY | 
| Owners Name and Address
 Commencement date  | 
REPUBLIC OF TURKEY MINISTRY OF NATIONAL DEFENCE NATO. INF. DEPT.14.03.1989  | 
| Completion date | 29.05.1992 | 
| Operating Firm | E.H ARUTAN. Inc | 
| Associated Firms | None | 
| Description of project | This project consisted of the following contruction works withinThe POL (Petroleum Oil Lines) 1 each 10.000 cu.m Steel Fuel Storage Tank coveredwith Reinforced-concrete5 each 5.000 cu.m Steel Fuel Storage Tank covered with Reinforced-concrete2 each 2.500 cu.m Steel Fuel Storage Tank covered with Reinforced-concrete2 each 1250 cu.m Steel Fuel Storage Tank covered withReinforced-concrete 8 each 100 cu.m Steel Sedimentation Tank. 10 each 10 cu.m Steel Drainage Tank Manifolds and water separator/filtration stations  | 
| Description of project(cont’d) | Truck loading locations
 Pump pats Bute connecting piping and scraper trap connections 5 KM Long 6” Diaweter Fuel Pipeline between MUŞ province Tank Farm and Airbase 
 
  |